38. A perusal of the above judgment leaves no manner of doubt that this Court has held that in terms of Order XLVII Rule 5 of CPC, a review should normally be heard by the same Bench which passed the original order. We may reiterate the reasons given by this Court. These are :- 1) The judges who heard the matter originally have applied their mind and would know best the facts and legal position; 2) They will be in the best position to appreciate the matter in issue when a review is filed; 3) If the matter goes before another Bench that Bench will have to virtually hear the matter afresh; 4) Most importantly, when the matter goes to a new Bench the members of the new Bench may go by their own perspective and philosophy which may be totally different to that of the Bench which originally heard the matter. We may again re-emphasize that judicial discipline, judicial traditions and consistency in pronouncements require that the Bench which heard the matter originally should hear the review petition unless it is virtually impractical for the original Bench to hear the matter, or where the members of the original Bench recuse.
39. Another ground raised is that the statutory appeal was already pending in this Court against the original order when the review application was taken up for hearing. It is contended, on the basis of Order XLVII Rule 1(2) of CPC, that review application should not have been taken up for hearing because the original applicant could have before this Court taken up all the points which he had taken in his review application. It is also contended that this is not a case where there is an error apparent on record and as such the power of review could not have been exercised. As far as the facts of this case are concerned we are clearly of the view that the original applicant could have raised all issues which he raised in review application even by filing a counter affidavit in the appeal filed by the project proponent or by challenging the original order in this Court as he has done now. In this context, once this Court was seized of the matter and all issues were being urged, the NGT should not have proceeded to hear the review application.
40. We may add that on 21.12.2016, the review application itself was listed before the Bench of Dr. Justice Jawad Rahim and Dr. Ajay A. Deshpande, which adjourned the matter to 25.01.2017 to hear it regarding maintainability of the review application in view of the statutory appeal provided under the National Green Tribunal Act, 2010. However, the matter got listed before the other Bench and on 25.07.2017, the said Bench considered this objection raised by the project proponent in terms of Order XLVII Rule 1 of the CPC and the Bench held as follows: “Having perused the record, we find that the Appellant is seeking quashing of the order of compensation in totality and the Review Applicant is seeking enhancement of the compensation granted by the Tribunal. We do not see any commonality in the grounds resorted to by the Applicant and Appellant in the said Appeal. Exception to Sub-clause 2 of Order 47 Rule 1 of Code of Civil Procedure, therefore, does not come to the help of Respondent No.9. We are, therefore, of the considered opinion that the Review Application is maintainable. Plea of non-maintainability of the Review Application is rejected.” M/S. GOEL GANGA DEVELOPERS v. U.O.I.THR. SECY. MINISTRY OF ENVIRONMENT [DEEPAK GUPTA, J.]
41. We are of the view that the aforesaid finding is incorrect. The project proponent had not only challenged the original order of the NGT on the ground that he had not violated the EC but also on the ground that the damages awarded were highly excessive. Therefore, the question that what should be the extent of damages was specifically before this Court. We are therefore, clearly of the opinion that the Bench hearing the review application erred in holding that the review application was maintainable despite the appeal pending before this Court.
42. We may also note that the Bench which heard the review has rejected all other grounds of review mainly on the ground that there is no error apparent on the face of the record but has only dealt with the issue of enhancement of damages to be imposed on the basis of ‘Carbon Footprint’ relying on the affidavit dated 18.05.2016. The Bench noted that this affidavit had not been taken into consideration by the earlier Bench. How could the latter Bench hearing the review application know whether any reference was made to this affidavit at the time of original hearing or not? In fact, the project proponent urges that this affidavit was never filed on 18.05.2016.
43. Here, it would be pertinent to mention that according to the original applicant he was given oral permission by the Bench to file such an affidavit on 23.02.2016. We have perused the order dated 23.02.2016 and find that it makes no mention of any such request being made. If there is no such request then the question of issuing an oral direction to file such an affidavit does not arise. We may also add that after 23.02.2016, the matter was listed on numerous occasions i.e. 16.03.2016, 05.04.2016, 18.04.2016, 22.04.2016, 02.05.2016 and 05.05.2016 before the NGT. In none of the orders there is any reference to Carbon Footprint or to any affidavit to be filed by the original applicant. If an oral permission had been given, obviously the original applicant would have either filed an application or would have made a request that he wants to file such an affidavit.
44. The affidavit in question is dated 18.05.2016 and it is alleged that it was filed on 18.05.2016. The matter was listed for hearing on 19.05.2016 on which date also there is no reference to any such affidavit. It would be pertinent to note that in between the project proponent had filed an M.A. No. 389 of 2016 before the Principal Bench stating that an interim order dated 23.12.2015 had been passed against it and the matter was not being heard and, therefore, it may be heard by a Bench presided over by Dr. Justice Jawad Rahim, who apparently was holding Court in the Pune Bench at that time and the Principal Bench allowed the same on 02.05.2016 directing that the matter be listed before the Bench presided over by Dr. Justice Jawad Rahim. On 19.05.2016, the original applicant sought time stating that he had filed review application against the order dated 02.05.2016 before the Principal Bench praying that the matter should be heard by the earlier Bench presided over by Justice U.D. Salvi and, therefore, the matter could not be heard by Dr. Justice Jawad Rahim on that day and was further adjourned to 23.05.2016. There is no reference to Carbon Footprint in the order dated 19.05.2016. On 23.05.2016, the matter was heard by the Bench presided over by Dr. Justice Jawad Rahim and the orders reserved. In this order also there is no reference to the affidavit with regard to Carbon Footprint. If the filing of the affidavit would have been brought to the notice of the Bench, it would have recorded in the order that some fresh affidavit had been filed. Subsequently, the project proponent, who is the contesting respondent, filed an application on 20.07.2016 praying that in the meantime he had obtained permission of the Environment Department and the SEIAA to which we have adverted hereinabove.
45. The original applicant sought time to file counter affidavit. The matter was adjourned to 28.07.2016 for re-hearing deleting the same from reserved list since there were subsequent developments. On 28.07.2016 the matter was got adjourned to 02.08.2016 on which date some execution application for implementation of the interim orders was taken up and direction was issued to the PMC. The matter was again taken up on 08.08.2016, 19.08.2016 and 24.08.2016 when the hearing was closed and judgment was pronounced through video conferencing on 27.09.2016. In none of these orders any mention was made for Carbon Footprint or to the affidavit on the basis of which the review application was filed. On 23.05.2016 the project proponent filed reply to the affidavit dated 18.05.2016 filed by the original applicant in which they raised objections that such affidavit was not filed on 18.05.2016 and the copy of the same was handed over to them on 20.05.2016 and the original applicant had no permission to file such an affidavit. All these disputed issues as to whether such an affidavit was filed with the permission of the Court or it was referred to in the first hearing or in the second hearing could only be decided by the Bench which had heard the matter on 23.05.2016 or on 24.08.2016 on which dates the original application was reserved for orders. M/S. GOEL GANGA DEVELOPERS v. U.O.I.THR. SECY. MINISTRY OF ENVIRONMENT [DEEPAK GUPTA, J.]
46. We are of the considered view that the review application should have been heard by a Bench headed by Dr. Justice Jawad Rahim who was admittedly available and in fact continues to be a member of the NGT. Therefore, we are constrained to set aside the order passed in Review Application No.35 of 2016 dated 08.01.2018 Is Demolition the only answer?:
47. The next issue which arises is that what we should do with the construction. A large number of flats are already occupied and a large number of persons have paid money for occupying these flats. Learned counsel appearing for those persons who have purchased the flats urged that the flats should not be demolished otherwise they shall be put to great monetary loss. As pointed out above now there are 807 flats and 117 shops which are either constructed or under construction. These flats are 1, 1.5 and 2 BHK flats and small shops and offices. The project proponent has already taken money from these persons and a large number of flats and shops have already been occupied and even where the remaining flats and shops are not occupied, persons belonging to the middle class have invested their life’s earnings in this project. Keeping in view the interest of these third parties who were not parties before the NGT, we are of the view that in the peculiar facts and circumstances of the case, demolition is not the answer. This would put innocent people at loss. Normally, this Court is loathe to legalize illegal constructions but in the present case we have no option but to do so.
48. We hasten to clarify that the project proponent cannot be permitted to build any more flats. What we are permitting him to do is to only complete construction of 807 flats, 117 shops/offices and cultural centre including the club house. We make it clear that he shall not be allowed to build the two buildings in which he was to construct 454 tenements, and will obviously have to return the money with interest at the rate of 9% per annum to the individual(s) who have invested in the same. There is no equity in favour of these persons since the plan to raise this construction was submitted only after 2014 when the validity of the earlier EC had already ended. Therefore, though we uphold the order of the NGT dated 27.09.2016 that demolition is not the answer in the peculiar facts of the case, we also make it clear that the project proponent cannot be permitted to build nothing more than 807 flats, 117 shops/offices, cultural centre and club house. Whether the Original Applicant is entitled to Special Damages:
49. On behalf of the original applicant various issues were raised before us which had not been raised before the NGT and find no mention either in the original order or even in the order under review. We are not considering those issues. It was urged that the project proponent has reduced the area of Cultural Centre. This averment is not correct as pointed by senior counsel appearing for the Union of India. The development plan is not only for the area under the project but covers a much larger area where more than one builder and projects may be involved. It is not the responsibility of only one builder to provide the entire community services and these have to be provided pro rata by all developers of projects in the area. It was also alleged that the builder had built 3 basements which are illegal. On the other hand it was contended by the learned senior counsel for the project proponent that one of the basements has already been blocked and the other two basements shall also not be put in use and would be completely blocked off. We make it clear that PMC and SEIAA will ensure that the project proponent blocks the basements in such a manner that they can never be put to any use. Another argument raised by the original applicant was that the project proponent had stated that though he would not use any ground water, however it has utilized the ground water and violated the condition of the EC. Reliance is placed on certain photographs showing water being pumped. On the other hand on behalf of the project proponent it has been urged that this water was being pumped out from the excavated area when the building was built and the water level had risen. We cannot decide this disputed question of fact in these proceedings.
50. We may also point out that in this case the original applicant has tried to project the case as if he is filing the case in the public interest and has prayed for certain general directions. He has also claimed special damages for himself. The main grievance of the original applicant is with regard to the violation of the EC and according to him these violations started in the year 2009. The original applicant had applied for a flat in the project in question and had issued notice to the project proponent on 21.10.2011 about deficiency in service. This notice was replied to on 17.11.2011. Thereafter, the original applicant filed Consumer Complaint No. 95 of 2012 on 22.02.2012. This complaint was decided on 20.11.2014. Thereafter, the order of the District Consumer Disputes Redressal Forum was challenged before the State Consumer Redressal M/S. GOEL GANGA DEVELOPERS v. U.O.I.THR. SECY. MINISTRY OF ENVIRONMENT [DEEPAK GUPTA, J.] Commission both by the project proponent and original applicant in February, 2015. It appears that thereafter there were complaints and counter complaints filed by the parties against each other and the project proponent filed a civil suit for defamation against the original applicant on 02.12.2015 and it was only thereafter on 07.12.2015 an application was filed in the NGT by the original applicant. We are highlighting these facts only to emphasize the fact that this litigation is obviously not a Public Interest Litigation. Therefore, the claim of the original applicant to award him special damages cannot be accepted. Quantification of damages:
51. We need to decide and re-assess the issue of damages since the original applicant has also challenged the original order of the NGT. While assessing the damages we may note certain facts:- 1) The EC was granted on 04.04.2008 but construction commenced after issuance of consent to establish dated 20.06.2009 and the EC would be valid for a period of 5 years from the date of such consent, i.e. upto 19.06.2014; 2) The EC dated 04.04.2008 was granted for construction of built up area 57,658.42 sq.mtrs., whereas admittedly, as of now the constructed built up area is 1,00,002.25 sq. mtrs.. Therefore, there is clear-cut violation of the terms of the EC; 3) Any construction raised after 19.06.2014 is without any EC especially since we have held that EC granted on 20.11.2017 is invalid. Carbon Footprint:
52. The main case of the original applicant is that the damages should be assessed on a scientific basis by calculating the damage caused to the environment by the project proponent on the basis of ‘Carbon Footprint’. In the absence of detailed submissions, we find ourselves totally unequipped to go into this aspect of the matter.
53. In the original application filed by the original applicant before the NGT, there is no reference to Carbon Footprint. Even when evidence was initially led, no reference was made to the same. The concept of Carbon Footprint was introduced by the original applicant only in his affidavit dated 18.05.2016. In fact, according to the project proponent this affidavit was not even filed on 18.05.2016. It appears to us that there is no order of the NGT specifically permitting the original applicant to file such an affidavit. The submission of original applicant is that he was orally permitted to file the same. These disputed questions would have been only decided by the Original Bench and, therefore, we have already set aside the order passed in the review application dated 08.01.2018.
54. Courts cannot introduce a new concept of assessing and levying damages unless expert evidence in this behalf is led or there are some well established principles. We find that no such principles have been accepted or established in the present case. When there are no pleadings in this regard we fail to understand how the concept of Carbon Footprint can be introduced after evidence has been closed, at the stage of arguments. We cannot assess the impact in actual terms and, therefore, we can only impose damages or costs on principles which have been well settled by law.
55. We may also note that the method to which the original applicant referred to is not part of any law, rule or executive instructions. This method is no doubt used to compensate and impose damages on nations but we cannot apply this method while imposing damages on a person who violates the EC. We may also add that the calculation made by the original applicant in his affidavit dated 18.05.2016 filed before the NGT are based on assumptions some of which we have not found to be correct namely – (1) use of ground water; (2) reduction of Cultural Centre space; (3) construction of basements etc..
56. We may make it clear that we are not laying down the law that damages cannot be assessed on the basis of Carbon Footprint. In a case where expert evidence in this behalf is led or on the basis of empirical data it is established that by applying the principles of Carbon Footprint damages can be assessed, the Court may, in the facts and circumstances of the case, rely upon such data but, in the present case, there is no such reliable material.
57. Having held so we are definitely of the view that the project proponent who has violated law with impunity cannot be allowed to go scot-free. This Court has in a number of cases awarded 5% of the project cost as damages. This is the general law. However, in the present case we feel that damages should be higher keeping in view the totally intransigent and unapologetic behaviour of the project proponent. He has maneuvered and manipulated officials and authorities. Instead of 12 buildings, he has constructed 18; from 552 flats the number of flats has M/S. GOEL GANGA DEVELOPERS v. U.O.I.THR. SECY. MINISTRY OF ENVIRONMENT [DEEPAK GUPTA, J.] gone upto 807 and now two more buildings having 454 flats are proposed. The project proponent contends that he has made smaller flats and, therefore, the number of flats has increased. He could not have done this without getting fresh EC. With the increase in the number of flats the number of persons, residing therein is bound to increase. This will impact the amount of water requirement, the amount of parking space, the amount of open area etc.. Therefore, in the present case, we are clearly of the view that the project proponent should be and is directed to pay damages of Rs.100 crores or 10% of the project cost whichever is more. We also make it clear that while calculating the project cost the entire cost of the land based on the circle rate of the area in the year 2014 shall be added. The cost of construction shall be calculated on the basis of the schedule of rates approved by the Public Works Department (PWD) of the State of Maharashtra for the year 2014. In case the PWD of Maharashtra has not approved any such rates then the Central Public Works Department rates for similar construction shall be applicable. We have fixed the base year as 2014 since the original EC expired in 2014 and most of the illegal construction took place after 2014. In addition thereto, if the project proponent has taken advantage of Transfer of Development Rights (for short ‘TDR’) with reference to this project or is entitled to any TDR, the benefit of the same shall be forfeited and if he has already taken the benefit then the same shall either be recovered from him or be adjusted against its future projects. The project proponent shall also pay a sum of Rs. 5 crores as damages, in addition to the above for contravening mandatory provisions of environmental laws.
58. Normally, this Court is not inclined to grant ex post facto EC. However, in the peculiar facts of this case we direct that once the project proponent deposits the amount of damages as directed by us then the project proponent may approach the appropriate authority for grant of EC. The authority may impose such conditions for grant of EC as it deems necessary. Findings and Directions:
59. We summarise our findings and directions as follows: (i) That built up area under the notification of 14.09.2006 means all constructed area which is not open to the sky; (ii) Built up area under the notification of 04.04.2011 means all covered area including basement and service areas; (iii) The communication dated 07.07.2017 is totally illegal and accordingly quashed; (iv) The original application cannot be treated as a public interest litigation; (v) We are not taking note of the allegations levelled against the individuals who have not been arrayed as parties; (vi) That the order dated 27.09.2016 of the NGT is upheld except in so far as Direction No. 1 is concerned; (vii) The order in review application passed by the NGT on 08.01.2018 is held to be totally illegal and is accordingly set aside; (viii)We uphold the original order dated 27.09.2016 holding that the construction raised by the project proponent was in violation of the environmental clearance granted to it on 04.04.2008. We uphold the fine imposed upon the PMC and the direction given to the PMC to take appropriate action against the erring officials. We also uphold the direction given to the Chief Secretary to the State of Maharashtra and in addition, direct that the Chief Secretary to the State of Maharashtra shall look into the conduct of the official holding the post of Principal Secretary (Environment) to the Government of Maharashtra on 27.09.2016 and will submit his report to the NGT within three months from today; (ix) We impose damages of Rs.100 crores or 10% of the project cost, whichever is higher on the project proponent and in addition thereto, project proponent will pay Rs.5 crores as levied by the NGT in its order dated 27.09.2016; (x) Project proponent shall not be permitted to raise construction of two buildings having 454 tenements; (xi) We direct that the project proponent shall only be permitted to complete construction of a total 807 flats, 117 shops/offices and cultural centre including club house; (xii) The project proponent will only be permitted to seek environmental clearance for completion of the project subject to payment of costs in the aforesaid terms and it may be granted ex post facto environmental clearance in the peculiar facts of M/S. GOEL GANGA DEVELOPERS v. U.O.I.THR. SECY. MINISTRY OF ENVIRONMENT [DEEPAK GUPTA, J.] the case, on such terms and conditions as the environmental authority deems fit and proper; (xiii)The project proponent is granted six months’ time to deposit the amount of damages imposed in terms of direction no. (ix) supra in the Registry of this Court. In case the project proponent does not deposit the amount within six months then all the assets of the project proponent i.e. M/s. Goel Ganga Developers India Pvt. Ltd. as well as its Directors shall be attached and the amount of damages shall be recovered by sale of those assets. It is further directed that in case this amount is not deposited within the period of six months then the licence/registration/permission granted to M/s. Goel Ganga Developers India Pvt. Ltd. to develop any “real estate project” within the meaning of the Real Estate (Regulation and Development) Act, 2016 shall be cancelled and the project proponent i.e. M/s. Goel Ganga Developers India Pvt. Ltd. and its Directors shall not be granted permission to develop any “real estate project” under the Real Estate (Regulation and Development) Act, 2016 without permission of this Court. (xiv)The matter be listed on 22.10.2018 for issuing appropriate directions as to how the amount of damages are to be utilised;
60. All the appeals are disposed of in the aforesaid terms. Pending application(s) if any, shall also stand disposed of. Ankit Gyan Appeals disposed of.